How to better install anti-static floor?

Update:12-01-2021
Summary:

First. Requirements for laying site 1. The laying of th […]

First. Requirements for laying site
1. The laying of the floor should be carried out after the completion of indoor civil construction and decoration;
2. The ground should be flat, dry, free of debris and dust;
3. The usable space under the floor, the layout and laying of cables, circuits, waterways, air and other pipes and air conditioning systems should be completed before installing the floor;
4. The fixing of the base of large heavy equipment should be completed, and the equipment should be installed on the base. The height of the base should be the same as the height of the finished surface of the floor;
5. 220V/50HZ power supply and water source are available on the construction site.

 

 

Second. Floor installation and laying tools
1. Marble cutting saw; 2. Laser level meter, network laser scanner; 3. Water bubble level, tape measure, ink line; 4. Suction plate, nut adjustment handle, Phillips screwdriver; 5. Vacuum cleaner, broom, mop ;

Three, construction steps
1. Carefully check the flatness of the ground and the verticality of the wall. If there are major defects or partial modifications are found, they should be submitted to the relevant departments of Party A;
2. Pull the horizontal line and use the ink line to bounce the installation height of the floor to the wall to ensure that the laid floor is at the same level. Measure the length and width of the room and select the reference position, and pop up the network grid line of the installation support on the ground , To ensure the laying is neat and beautiful, while minimizing the cutting of the floor;
3. Adjust the support to be installed to the same required height and swing the support to the cross point of the ground grid line;
4. Fix the truss beam to the support with mounting screws, and use a horizontal ruler and a square to correct the truss beam one by one so that they are both in the same plane and perpendicular to each other;
5. Place the raised floor on the assembled truss beam with a plate suction device;
6. If the remaining size near the wall is less than the length of the raised floor, it can be patched by cutting the floor;
7. When laying the floor, level it block by block with a bubble level. The height of the raised floor is adjusted by the adjustable support. During the laying process, it should be handled with care to prevent scratching the floor and damaging the side strips. At the same time, it should be cleaned while laying. , Avoid leaving debris and dust under the floor;
8. When installing heavier equipment in the machine room, a support can be installed under the floor of the equipment base to prevent the floor from deforming;
9. When the HPL decorative board needs cutting or opening processing, φ6~φ8 crack stop holes should be made at the concave corner of the opening to prevent cracking of the processed floor decoration surface.